November 7, 2024 in News
Enabling Action: Recognising World Ventil8 Day
Ventilation is key to achieving healthy buildings and healthy lives – whether it is where you work, live, study or spend your leisure time.
Working under a Built Obayashi Joint Venture, ¶º±ÈÖ±²¥ has played a key role in the construction of the new $175 million 3 Parramatta Square building for developer, the Walker Group. This venture with BOJV has also successfully delivered the neighbouring commercial tower in the Parramatta Square precinct.
The 3 Parramatta Square mixed-use tower features the architectural design by Johnson Pilton Walker (JPW) over 43,000m² of A-Grade office space across 16 levels. Central within the building is an open atrium starting above the Ground floor and spanning the entire tower allowing natural light through a glass ceiling above to illuminate the interior. The building also features three Basement car parking levels below plus a Basement Mezzanine level with end-of-trip facilities. Multiple retail spaces are located along the Ground floor to face the greater promenade from Parramatta Station.
Following its engagement as a full design and construct mechanical services contractor in 2017, ¶º±ÈÖ±²¥ worked collaboratively with base building consulting engineers LCI for the base building design and Norman Disney & Young (NDY) on the integrated NAB fit-out. With the first 13 floors of the tower tenanted by NAB, ¶º±ÈÖ±²¥ worked with the fit-out architects Woods Bagot and project manager Savills to deliver an integrated fit-out concurrently with the base building.
¶º±ÈÖ±²¥ led the development to adopt a hybrid system for the base building that features an efficient passive chilled beam arrangement serving the floorplate perimeter, and a low-temperature variable air volume (VAV) system across the open office floors. A high-temperature chilled water system supplying the chilled beams is provided through a secondary heat exchanger arrangement with the main chilled water plant.
Several adaptive prefabrication techniques were utilised by ¶º±ÈÖ±²¥ to expedite the services installation and minimise time on site. These included the offsite prefabrication of approximately 350 modular frames featuring chilled beams manufactured in Denmark. By prefabricating the frames offsite, each chilled beam could be pressure tested after assembly to identify potential defects in the factory prior to their installation across Levels 3 to 16.
Approximately 90+ meeting and comms rooms located across Levels 1 to 13 (tenanted by NAB) are served by separate packaged units fed by the tenancy condenser water loop. To simplify the manufacture and installation to a consistent quality, ¶º±ÈÖ±²¥ consolidated their design into three typical acoustically treated box modules.
Prefabricated offsite, the acoustically treated packaged unit modules were able to be quickly mounted and connected to services in the ceiling above each meeting room saving significant site installation works.
In its lead services role ¶º±ÈÖ±²¥ also implemented the use of building information modelling (BIM) software on the project and were the lead modelling coordinators of the 3PS project.
Furthermore, site utilisation of BIM models on handheld devices allowed visibility of installation during construction preventing many potential clashes through quick resolution.
Practical completion at 3 Parramatta Square was reached in April 2020. NAB’s lease commencement was scheduled for the beginning of July, however to manage workplace exposure to COVID-19, NAB occupation of the building has pushed back to August 2020.
Post completion, ¶º±ÈÖ±²¥ have been engaged to provide ongoing service and maintenance to both the 3 and 4 Parramatta Square buildings showcasing an ¶º±ÈÖ±²¥ Whole-of-Life delivery.
Project Name: Parramatta Square
Location: Parramatta, NSW
Client: Built Obayashi Joint Venture
Year Completed: 2021
Design & Construct
November 7, 2024 in News
Ventilation is key to achieving healthy buildings and healthy lives – whether it is where you work, live, study or spend your leisure time.
November 6, 2024 in Advisory Notes
Modern fire protection systems are now often integrated into other building systems and require a comprehensive testing approach to assure they will o...
November 1, 2024 in News
Together we achieve the extraordinary – and that culture of strength and high performance was on full display at the 2024 ¶º±ÈÖ±²¥ Annual Dinner ...
October 21, 2024 in News
Progressive organisations are constantly reviewing their place in the world, and what their brand represents. Creating a culture that actively address...